Bored  Precast  Piles

Bored  Precast  Piles

Bored  precast concrete  piles  are  constructed  in  a casting  yard  and  subsequently  lowered  into  prebored  holes and  the  space  grouted.

As  far  as  possible,  in-situ  extensions  shall  be avoided.The  casting  yard  should  be  well  drained. As  far  as  possible,  longitudinal  reinforcement shall  be  in  one  length.  In  case  joints  are needed,  they  should  be  staggered.The  hoops  and  links  for reinforcement  shall  fit tightly  against  the  longitudinal  bars  and  be bound  to  them  by  welding  or  by  tying  with binding  wire,  the  free  ends  of which  should  be turned  into  the  interior  of  the  pile.  The  longitudinal  bars  may  be  held  apart  by  temporary or  permanent  spreader  forks  not  more  than 1.5 m apart.  The  reinforcement  shall  be checked  for  tightness  and  position  immediately before  concreting. After  casting  the  piles,  they  shall  be  stored  as described  in

Bored  precast  piles  shall  be .constructed  by suitable  choice  of boring  and  installation  techniques  depending  on  detailed  information about  the  subsoil  conditions.  The  bottom  end of  the  pile  shall  have  proper  arrangements  for cleaning  and  grouting.

Piles  shall  be  installed  as vertically  as possible according  to  the  drawings,  or  to  the  specified batter.The  deviation  from  specified  alignment shall  be  as permitted  for under-reamed  piles.

Cement  and  sand  (1 : 2) grout  mixed  with  water in a high  speed  colloidal  mixer  is fed to the pile with  grout  pump  of  suitable  capacity  to  the central  duct  through  a  manifold.  Temporary casing  used  here  shall  be  removed  in  stages with  the rise  of level  of grout.  The  grout  should be  levelled  off  at  the  top.  The  strength  of  the grout  shall  be  at  least  equal  to  the  strength  of the  surrounding  soil.

Where  a pile  is  to  have  another  length  cast  on to  it before  or  during  placing,  the  longitudinal reinforcement  should  be  welded  with  full penetration  butt  welding,  after  the  concrete  at the  top  of  the  pile  should  be  cut-off  to  expose not  less  than  200  mm  of the  bars.  Bars  may  be lapped  if  it  is  not  possible  to  undertake  butt welding  with  an  overlap  of 40  times  the  dia  of bar.